13/03/2024
NORECO II would like to inform you that there will be a scheduled power service interruption.
CHANGE IN DURATION
Date of Interruption: March 16, 2024 (Saturday)
Time: 6:00 A.M. to 6:00 P.M. (instead of 6:00 A.M. to 4:00 P.M.)
Areas Affected: Feeder 1 and Feeder 3 of Pulantubig Substation
Feeder 1
• portion of Pulantubig (from NORECO II Pulantubig Substation to crossing Saint Paul University), along the national highway (from crossing Saint Paul University to Dumaguete-Sibulan City Limit), Buñao and West Bantayan in Dumaguete City
• Bolocboloc, Dumaguete–Sibulan Airport, Agan-an (including Negros Oriental Police Provincial Office), Maslog, Negros Polymedic Hospital, Tubtubon (from Orient Woods to Philippine Benevolent Missionaries Association Inc./PBMA), Cangmating (including Sibulan Ice Plant, DPWH office and Casa Mira Coast), Sibulan proper, Campaclan, Kabulakan, Okoy, Mainit, Looc, Upper Pansil, Lower Pansil, Bravo Golf Hotel Resort & Spa, Cansaging, Candaol, San Antonio, Tubigon, Ata-ata, Balili, Balugo, Maningcao Gamay, Maningcao Dako, Cantalawan, Ajong, Cansal-ing and Butigon in Sibulan
• Balili in Valencia
• Calo, Naiba and Naupak in San Jose
Feeder 3
• along the national highway (from Qualfon to Tree Hive Guest House in front of NORSU), RM Building, Qualfon, CitiHomes, CityMall, Villa Amada, Negros Oriental Provincial Hospital, Lasola Drive, E.J. Blanco Ext., Maria Asuncion Village, Claytown Daro, Swan Lake, Little Children of the Philippines Foundation, Inc., ACE Dumaguete Doctors, Inc., SUMC, Silliman University Power House, Aldecoa Drive, Metro Dumaguete Waters, Palms and Pines, Cang's Incorporated Shopping Complex, Capitol area, NOHS, NORSU, DepEd Division Office of Negros Oriental, NBI Dumaguete District Office, Lamberto L. Macias Sports & Cultural Complex and Negros Oriental Convention Center in Dumaguete City
REASON: As this is a two-part activity, NORECO II will maximize the downtime on March 16, 2024. This is to lessen the downtime during the second part of the activity, the date of which is yet to be
finalized.
All works may be finished ahead of time and power may be restored earlier than scheduled, so please consider the lines always energized. Member-customer-owners in the affected areas are advised to take the necessary precautions. Please turn off all your electrical switches and once power is back, please wait for five minutes before switching on your electrical switches.
Thank you for understanding.
By: Negros Oriental II Electric Cooperative - NORECO II